Project:

Cydnerth (Morlais)

Overview:

The Growth Deal investment will fund an expansion of the Morlais project called Cydnerth, which will develop an additional grid connection allowing tidal energy developers to deploy more turbines within the Morlais zone. The proposed expansion will create new jobs and supply chain opportunities for the region and additional capacity to generate renewable energy.

Morlais is located off the northwest coast of Holy Island, Anglesey and aims to generate electricity through tidal energy. Once the infrastructure is in place, it will use some of the best tidal resources in Europe.

Ambition North Wales is working with lead sponsor, Menter Môn to develop this project.

Lead Sponsor:

 

Objectives

Additional GVA

Generate up to £30 million net additional GVA

Job Creation

Create up to 100 new jobs for the region

Low Carbon Energy

Generate at least 100MW electricity from tidal stream energy

Target Investment

£9m

Growth Deal

£0m

Public Sector

£0m

Private Sector

£9m

Total Investment

Which stage has the project reached?

Stage01.
Determine the Project context:

The planning phase of the spending proposal. Assessing the strategic context for the project and demonstrating how it provides synergy with other projects within the portfolio.

Check icon progress icon Complete
Stage02.
Preparing the Strategic Outline Case:

The scoping phase of the project. Making the case for change and identifying the preferred way forward.

Check icon progress icon Complete
Stage03.
Preparing the Outline Business Case:

The planning phase for the project. Identifying the options that provide value for money, confirming the affordability of the project and determining the arrangements for the successful delivery of the project. 

Check icon progress icon Complete
Stage04.
Approval of the Outline Business Case:

The Outline Business Case is presented to the North Wales Economic Ambition Board for approval. When approved the procurement phase of the project can begin. 

Check icon progress icon Complete
Stage05.
Preparing the Full Business Case:

The procurement phase of the project. Recording the findings of the procurement and confirming the management arrangements for the delivery, monitoring and evaluation of the project.  

Check icon progress icon In Progress
Stage06.
Approval of the Full Business Case:

The Full Business Case is presented to the North Wales Economic Ambition Board for approval. When approved the implementation phase of the project can begin. 

Check icon progress icon
Stage07.
Project Implementation and Monitoring:

The project implementation phase. The Full Business Case is used as a reference point to deliver the project and monitor progress. 

Check icon progress icon
Stage08.
Project Evaluation:

The post project implementation stage. Evaluating how well the project was delivered and lessons learnt.  The Full Business Case is used to determine the extent the anticipated benefits were delivered and realised.

Check icon progress icon

Key Members

  • Gerallt Llewelyn Jones Menter Môn
  • Elgan Roberts Low Carbon Energy Programme Manager