Project:

Warren Hall, Flintshire

Overview:

This project will involve providing primary services such as power, telecoms and water to the site. It will also level the ground so that it’s suitable for employment and business premises. The aim is to attract private sector investment and create opportunities for businesses to relocate and expand. It will also create new job opportunities.

The site is in Broughton, Flintshire, near the A55 expressway and the Deeside Employment area.

Ambition North Wales is working with Welsh Government to develop this site.

Lead Sponsors:

 

Objectives

Additional GVA

Generate up to £120 million net additional GVA 

Job Creation

Create up to 445 new jobs for the region

New Business Land

Developing land suitable for businesses

Investment Targets

£15m

Growth Deal

£0m

Other Public Sector

£55m

Private Sector

£70m

Total Investment

Which stage has the project reached?

Stage01.
Determine the Project context:

The planning phase of the spending proposal. Assessing the strategic context for the project and demonstrating how it provides synergy with other projects within the portfolio.

Check icon progress icon Complete
Stage02.
Preparing the Strategic Outline Case:

The scoping phase of the project. Making the case for change and identifying the preferred way forward.

Check icon progress icon In Progress
Stage03.
Preparing the Outline Business Case:

The planning phase for the project. Identifying the options that provide value for money, confirming the affordability of the project and determining the arrangements for the successful delivery of the project. 

Check icon progress icon
Stage04.
Approval of the Outline Business Case:

The Outline Business Case is presented to the North Wales Economic Ambition Board for approval. When approved the procurement phase of the project can begin. 

Check icon progress icon
Stage05.
Preparing the Full Business Case:

The procurement phase of the project. Recording the findings of the procurement and confirming the management arrangements for the delivery, monitoring and evaluation of the project.  

Check icon progress icon
Stage06.
Approval of the Full Business Case:

The Full Business Case is presented to the North Wales Economic Ambition Board for approval. When approved the implementation phase of the project can begin. 

Check icon progress icon
Stage07.
Project implementation and monitoring:

The project implementation phase. The Full Business Case is used as a reference point to deliver the project and monitor progress. 

Check icon progress icon
Stage08.
Project Evaluation:

The post project implementation stage. Evaluating how well the project was delivered and lessons learnt.  The Full Business Case is used to determine the extent the anticipated benefits were delivered and realised.

Check icon progress icon

Key Members

  • David Mathews Land and Property Programme Manager
  • Margaret Peters Land and Property Project Manager