Project:

Wrexham Gateway

Overview:

This project forms part of the Wrexham Gateway masterplan which aims to provide a framework of proposals to deliver a transformative mixed-use regeneration of the area.  The project will deliver approximately 7,000sqm of new office space at Wrexham Gateway. Aiming to deliver a sustainable development and vibrant regenerated area, creating a focal point to support business investment and a multi-modal transport hub. The masterplan will link active travel, placemaking and public realm projects to create a cohesive and vibrant environment.

This project will attract significant new jobs and investment to North Wales.

Ambition North Wales is working with lead sponsor Wrexham County Borough Council to develop this project.

Lead Sponsor:

Objectives

Additional GVA

Generate up to £10 million net additional GVA

Job Creation

Create up to 150 new jobs for the region

Investment Targets

£4.8m

Growth Deal

£0m

Other Public Sector

£9.6m

Private Sector

£14.4m

Total Investment

Which stage has the project reached?

Stage01.
Determine the Project context:

The planning phase of the spending proposal. Assessing the strategic context for the project and demonstrating how it provides synergy with other projects within the portfolio.

Check icon progress icon Complete
Stage02.
Preparing the Strategic Outline Case:

The scoping phase of the project. Making the case for change and identifying the preferred way forward.

Check icon progress icon Complete
Stage03.
Preparing the Outline Business Case:

The planning phase for the project. Identifying the options that provide value for money, confirming the affordability of the project and determining the arrangements for the successful delivery of the project. 

Check icon progress icon In Progress
Stage04.
Approval of the Outline Business Case:

The Outline Business Case is presented to the North Wales Economic Ambition Board for approval. When approved the procurement phase of the project can begin. 

Check icon progress icon In Progress
Stage05.
Preparing the Full Business Case:

The procurement phase of the project. Recording the findings of the procurement and confirming the management arrangements for the delivery, monitoring and evaluation of the project.  

Check icon progress icon
Stage06.
Approval of the Full Business Case:

The Full Business Case is presented to the North Wales Economic Ambition Board for approval. When approved the implementation phase of the project can begin. 

Check icon progress icon
Stage07.
Project Implementation and Monitoring:

The project implementation phase. The Full Business Case is used as a reference point to deliver the project and monitor progress. 

Check icon progress icon
Stage08.
Project Evaluation:

The post project implementation stage. Evaluating how well the project was delivered and lessons learnt.  The Full Business Case is used to determine the extent the anticipated benefits were delivered and realised.

Check icon progress icon

Key Members

  • Alistair Aldridge Wrexham Gateway Project Manager, Wrexham Borough Council
  • David Mathews Land and Property Programme Manager
  • Leanne Taylor Regeneration Project Manager, Wrexham County Borough Council